Overview

This stage of the project established the business need, reporting objectives and measurable requirements for the Azure DevOps Governance Analytics solution before development began.

The analysis translated a broad governance concern into specific reporting behaviours, business rules, KPIs and validation criteria that could be implemented and tested in Power BI.

Business Problem

Azure DevOps contained the information needed to monitor requirement approval activity, but the available work-item views did not provide a concise governance picture.

Users needed a reliable way to identify:

Without a consolidated analytical view, identifying these conditions required manual inspection of individual work items and provided limited visibility of the overall governance position.

Desired Outcome

The required solution needed to turn Azure DevOps data into a small set of decision-focused Power BI views that could support both operational follow-up and management oversight.

The final reporting structure was designed around four business-facing views:

  1. Executive Governance Overview — overall approval and requirements-health position.
  2. Approval Governance Summary — approval workload, overdue position and approval-age indicators.
  3. Overdue Approval Exceptions — actionable User Stories requiring approval follow-up.
  4. Requirements Health — objective assessment of requirements completeness and governance health.

A separate Validation / Model Validation page supports technical assurance and reconciliation.

Requirements Approach

Requirements were documented before implementation and converted into identifiable functional requirements, non-functional requirements, business rules, KPI definitions and success criteria.

Examples of the rules established during analysis include:

These rules created a controlled basis for Power Query transformation, semantic-model logic, DAX measures and subsequent validation.

Project Evidence

The examples below are selected from the controlled project requirements and demonstrate how the business problem was converted into measurable solution behaviour.

Selected Business Objectives

Objective Intended Outcome
OBJ-001 Reliably identify overdue approval requests using the current continuous approval period
OBJ-002 Enable targeted follow-up and clear current-authoriser accountability
OBJ-003 Provide consistent evidence-based governance monitoring and escalation
OBJ-004 Provide objective requirements-health classification and reasons
OBJ-005 Provide an executive summary of approval governance, requirements health and material exception concentration
OBJ-006 Provide consistent filtering, navigation and supporting detail

What this demonstrates:
The reporting solution was designed around defined business outcomes rather than beginning with dashboard visuals and fitting requirements around them afterwards.

Selected Functional Requirements

Requirement Requirement Example Delivered Through
FR-001–FR-006 Identify and present User Stories meeting the overdue-approval rules, including current responsible authoriser and approval age Overdue Approval Exceptions
FR-007–FR-014 Provide approval-governance KPIs including active requests, overdue requests, percentage overdue and approval-age measures Approval Governance Summary
FR-015–FR-026 Assess current User Stories using objective requirements-health rules and retain applicable health reasons Requirements Health
FR-027–FR-038 Present executive approval position, requirements health and material governance exceptions Executive Governance Overview
FR-039–FR-048 Provide consistent filtering, reset behaviour and navigation across the principal report pages Report interaction and navigation
FR-049–FR-052 Provide supporting row-level detail and controlled model/reconciliation validation Exception, health and validation views

What this demonstrates:
Requirements were expressed as testable reporting outcomes and mapped to specific parts of the implemented Power BI solution.

Selected Business Rules

Business Rule Area Rule Applied
Approval period The current continuous approval period is derived from the available Azure DevOps history and is used as the basis for approval-age calculation
Authoriser precedence Senior Authorised By takes precedence when both authorisation fields are populated, while each User Story is counted once
Overdue threshold Approval age uses whole calendar days, the approval-period start date is day zero and an active request becomes overdue at seven days
Requirements completeness Mandatory assessment includes Title, State, Area Path, Parent Feature, Description and Acceptance Criteria
Health classification Critical takes precedence over Attention Required; Healthy applies where no applicable issue exists
Health reasons All applicable health reasons are retained even where one overall status is displayed
Executive exceptions Material governance exception indicators may overlap and must not be interpreted as one additive population
Requirements requiring attention Critical and Attention Required are mutually exclusive overall statuses and can therefore be combined into a unique unhealthy population

What this demonstrates:
Business rules were separated from presentation design so the same definitions could be applied consistently through data preparation, semantic modelling, DAX, reporting and testing.

Selected Success Criteria

Success Criterion Expected Outcome
Approval accuracy Controlled overdue and non-overdue scenarios are classified correctly
Requirements health Controlled Healthy, Attention Required and Critical scenarios produce the expected classifications and reasons
Executive reconciliation Executive approval and requirements-health totals reconcile to the underlying current User Story population
Filtering and navigation Area Path, Iteration Path, reset controls and principal-page navigation behave consistently
Performance Principal report visuals remain within the defined Power BI performance thresholds
Portfolio release Public evidence contains only approved synthetic, anonymised or sanitised information

What this demonstrates:
Acceptance was defined in measurable terms, allowing the completed solution to be validated against expected behaviour rather than judged only by whether the dashboards appeared correct.

Evidence Presented

The public case study presents selected evidence from the controlled requirements phase, including:

The complete controlled Business Requirements Document remains part of the private project documentation, while the public case study presents the elements most useful for demonstrating the analysis and decision-making behind the solution.